Seattle-Tacoma International Airport's gleaming new $1 billion international terminal is a bust because it can't accommodate as many widebody planes as it was meant to - and it will cost millions to fix the mistake. The massive renovation to expand the airport's terminal was intended to simultaneously fit 20 large aircraft - but the end results in 2022 showed the facility could only hold 16, according to the airport operator, the Port of Seattle.Clark Construction, located in , was the company behind the design that is now being re-envisioned by the Port - and which will set it back $78 million to fix.